When New Canada Road Opens, Its Highway 70 End Will Still Be Two Lanes

What does "done" mean for a road that first showed up in a Memphis planning document in 1980? For New Canada Road, the answer comes in two parts. Under the current schedule, cars begin moving onto parts of the new road in late 2027, and the phase now under construction is expected to finish in fall 2028. At that point, the stretch from William Little Drive to Highway 70 will carry two lanes. The other two lanes, the landscaped median, the multi-use trails and a new traffic signal at Highway 70 belong to a second phase. The city says that phase will go out to bid only after the first one is finished.

The schedule makes more sense once you know where the road came from and why Lakeland split it up.

Where the Equipment Is This Fall

Anyone driving Canada Road north of I-40 lately has passed active work. The City of Lakeland's New Canada Road project page posted a September 21, 2026 update with three items. Curb and paving work was set to begin north of the Canada Road and Beverle Rivera Drive intersection. Earthwork and drainage were continuing at Canada Road and Memphis-Arlington Road. The city's October 14 management update adds a new front. Earthwork and drainage were scheduled to begin north of the Canabridge Road and New Canada Road intersection, and the city warned of construction equipment, trucks and noise.

There have already been short closures. William Little Drive was scheduled to close from Monday, September 28, through Thursday, October 1, for the project. At the Board of Commissioners meeting that same week, the agenda included a resolution on Change Order #2 with Chancellor Brothers, LLC, the Phase 1 contractor.

The city describes the finished road as a realignment of existing Canada Road between I-40 and Highway 70, about 2.3 miles long. It is planned as a four-lane divided road with landscaped islands and separate bike and pedestrian trails. In the early planning documents, widening the existing road, realigning parts of it, and building a new path that meets the old one at each end were all on the table. The version under construction is a new path, which is why some of the work sits away from the pavement drivers use today.

Four Decades on Paper

The Lakeland Banner's September 30 history of the project traces it back through the Memphis Metropolitan Planning Organization's records:

Year Milestone
1980 Canada Road corridor from U.S. 70 to I-40 appears in the Memphis MPO Long Range Transportation Plan
1992 Planning for a new alignment dates to at least this year
2006 The modern project, PIN 107036.00, enters MPO records
2008 Lakeland contracts with TDOT for an environmental assessment while a citizen and property-owner task force studies routes
2009–2011 Federal environmental and alignment studies cover wetlands, historic resources, noise and air quality
2014–2016 Right-of-way acquisition, with some parcels pursued through negotiation or condemnation
2020–2022 Texas Gas pipeline relocation, physically completed in summer 2022
2024 Estimated total cost reaches about $36 million, and the city decides to phase construction
2025 Phase 1 is bid in June and awarded to Chancellor Brothers, and construction begins in October

The city's project page adds a detail about the land. Right-of-way work involved easements on 50 tracts, acquired by Croft Associates under federal and TDOT procedures. Each step on that list had to be finished before the next one could start, and the last one in line was pricing the actual construction.

Why the Road Arrives in Two Pieces

Those prices are what produced the two-lane stretch at the north end. The Banner reports that by 2024 the full project's estimated cost had climbed to about $36 million. Lakeland chose to build in phases instead of all at once. Chancellor Brothers won the first phase, about 2.331 miles, with a bid of $24,177,910.65.

The city's own project page gives a different figure. It lists the anticipated cost of New Canada Road as nearly $25 million, paid 80 percent by federal Surface Transportation Block Grant funds managed by the Memphis MPO, with a $5 million local match. That is well below the Banner's $36 million estimate for the full project. The Banner notes that once the work was phased, funding broadened to include federal, state and local grants, city funds and debt proceeds. The city says its local share is backed by a USDA Rural Development loan and was included in the Fiscal Year 2026 General Fund budget.

According to the city's construction description, here is how the work divides:

Segment or feature Phase 1, now under construction Phase 2, bid after Phase 1 is finished
Beverle Rivera Drive to William Little Drive Four lanes Not listed
William Little Drive to Highway 70 Two lanes Final two lanes added
Landscaped median Not listed Included
Multi-use trails for pedestrians and cyclists Not listed Included
New traffic signal at Highway 70 Not listed Included

Put the table next to the Banner's schedule and the plan gets clearer. Traffic starts shifting onto portions of the road in late 2027, and the current phase wraps up in fall 2028. Phase 2 has no published date because it has no contractor yet. Whoever wins it will be approved after the first phase closes out. Both phase dates are projections, and the first already depends on change orders like the one commissioners took up on October 1. The trails and the Highway 70 signal, the parts most likely to change daily habits at the north end, are the furthest out.

The South End Finishes First

The four-lane segment starts at Beverle Rivera Drive, and that corner is getting a second large project on a similar timeline. The Lakeland Community Center YMCA is going up at Beverle Rivera Drive and Skyway Drive. It is about a 45,000-square-foot building, built with the YMCA of Memphis & the Mid-South. On October 8, the city invited residents to sign one of its structural beams. In his 2026 State of the City address, Mayor Josh Roman put the opening at late summer 2027.

That is roughly the season traffic is projected to start using parts of New Canada Road. If both schedules hold, the south end of the corridor will have a finished four-lane segment and a new community building at about the same time, while crews are still working toward Highway 70.

Lakeland Currents reported in June 2025 on what the approved design included:

  • A full basketball gym
  • Indoor and outdoor fitness areas
  • Early-learning childcare space
  • An eight-lane outdoor pool, with greenspace on the east side noted as a possible site for a future aquatic expansion

The same report put the projected cost at $21.3 million. Funding included a $4.8 million YMCA contribution, an $11 million USDA loan, an anticipated state grant for early learning, and Gateway TIF support. Under the agreement, the city owns the building and the YMCA runs daily operations and handles maintenance. Those numbers date to 2025 and were projections then. The YMCA's Lakeland location page already lists aquatics, swim lessons, pickleball, group fitness and early-learning programs. For current Senior Center users, the city says those programs continue and that it is planning future access to wellness amenities at the new center.

Pickleball players have another project to watch. The city secured a $963,000 grant from the Tennessee Department of Economic and Community Development for a six-court lighted pickleball complex on Huff N' Puff Road. No construction schedule has been published yet.

Meanwhile, on Today's Canada Road

Until traffic shifts in late 2027, existing Canada Road keeps carrying everything, and it hosts Lakeland's biggest fall event this weekend. The city's Harvest Festival runs Saturday, October 24, from 3 to 9 p.m. at IH Park, 4523 Canada Road. The lineup includes costume and pie-eating contests, goat snuggles, axe throwing, bounce houses and games. Rowdy and the Strays play live from 6 to 9 p.m.

The city's Thanksgiving food drive takes donations through November 18 at four drop-off sites. Food boxes are scheduled for pickup on November 21, 11 a.m. to 1 p.m., at the Parks and Recreation Office, 9845 Lake District Drive, Suite 103. For the next round of closures and work zones on the new road, the city's management updates and the project page are where the notices appear first.

If you own property near the Canada Road corridor, a road that opens in phases can affect how and when you sell, rent or renovate. Memphis Real Estate Advisors follows Lakeland projects like New Canada Road and the community center as part of our everyday brokerage and property management work. Ask for your free market report, and we'll show you how recent sales near the corridor compare with the rest of Lakeland.

Let’s Build the Right Strategy Together

Whether you’re buying, selling, or expanding an investment portfolio, Memphis Real Estate Advisors offers experience-driven guidance and personalized service. Connect with our team to start a real estate journey built on clarity, expertise, and long-term success.

CONTACT US